Bay Bridge Pump Station and Force Mains Replacement

Home >> Construction >> Bay Bridge Pump Station and Force Mains Replacement

CONSTRUCTION UPDATE

Work previously scheduled to take place over the current weekend has been rescheduled to start on Monday, January 19.

UPCOMING WORK

Crews will be working on the temporary shoring system on the launch pit, the entry point for the replacement of the new force mains, the sewer pipelines directly connected to the pump station.  Due to the nature of the work, 24-hour operations may be necessary.

Where: Next to OC San’s existing Pump Station

When: Week of January 19*

Hours: Starting at 7 a.m. on January 15. Hours may extend 24 hours a day, 7 days a week.*

What to Expect:

  • Lane and sidewalk closures on westbound Coast Highway
  • Heavy equipment and construction activity
  • Lighting to support safe operations for any nighttime work
  • Increased noise and activity around the work area

Bay Bridge bus stop closure by Dover

CURRENT WORK

Crews continue working on access pits to dig more than 50 feet below ground in support of constructing new force mains, the sewer pipelines that are directly connected to the pump station.

Locations:

  1. Launch Pit—Next to OC San’s existing Pump Station
  2. Receiving Pit—Shoulder of Eastbound Coast Highway past Dover Drive

These locations are the entry and exit points for the underground tunneling to install the force mains.

When: Ongoing–Spring 2026*

Hours: Monday–Friday, 7 a.m.–5 p.m.*

What to Expect:

  • Coast Highway is open to traffic in both directions.
  • Sidewalk closures near the work zone.
  • Increased activity, dust, and noise near the work areas during construction.
  • To minimize traffic impacts on Coast Highway, some activities may need to occur outside normal working hours.

Specific to Coast Highway and Dover Drive at Location #2:

  • K-rail is installed, temporarily closing the bus stop turnout. OCTA Stop 4933, Routes 1 & 55, are closed until further notice. Use the prior or next bus stop. Visit OCTA for more information.
  • Crossing path under Coast Highway is closed. Please take the appropriate detours.
  • Sound panels are installed by the nearest neighbors to mitigate noise.
  • We are working closely with the City of Newport Beach and Caltrans to minimize impacts and appreciate the community’s patience as we perform this work. The safety of the public and our crews remain our top priority.

*All dates and times are subject to change due to operational factors or inclement weather.

Project Description

This project will replace the existing Bay Bridge Pump Station located on Coast Highway between the Bay Bridge (east of Dover Drive) and Bayside Drive in the City of Newport Beach. The project will also replace the pressurized pipes, also referred to as force mains, consisting of two parallel pipelines which carry wastewater across the lower Newport Bay Channel. Wastewater then makes it way to OC San’s Reclamation Plant No. 2 in Huntington Beach.

Project Background

The Bay Bridge Pump Station was originally constructed in 1966 and is over 50 years old. The force mains are also over 50 years old. These critical assets are reaching the end of their useful life and need to be replaced to ensure they are reliable for the next 50 years. The new facility will be built to current structural and safety codes, making it safe and reliable to workers and the public.

The Bay Bridge Pump Station and Force Mains are located near pristine beaches along the Newport Channel Bay and is surrounded by residents, businesses, and visitors throughout the world. This pump station system transports between 4 to 18 million gallons of wastewater every day from the Newport Beach community. This project is needed to ensure we continue to collect, transport, and recycle Newport Beach’s wastewater safely while protecting the public health and the environment.

More information about the project can be found in the FAQ section.

CEQA: 

All CEQA documents can be viewed here.

Status: 

The project is currently in construction.

 

Local Sewer Maintenance: 

  • City of Newport Beach – Water and Wastewater Services – (949) 644-3011

Stay In The Know

Community Liaison:
(714) 378-2965

Email:
constructionhotline@ocsan.gov

Sign up for text alerts:
click here

Related Construction

Site Location

Construction Schedule

2025-2029

Construction Budget

$87.3 million